How long does it take to remodel in Corvallis?

How Long Does It Take to Remodel In Corvallis?

When you’re gearing up for a remodeling project, knowing how long it will take is key for planning and peace of mind. In Corvallis, just like anywhere else, the timeline for renovations can vary depending on what you’re doing. We’ll break down the remodeling timelines in Corvallis for the different types of projects we offer, such as sprucing up your kitchen or bathroom, giving your whole home a makeover, or even building a custom home. If you’re thinking about remodeling, this is a must-read guide!

Kitchen Remodels

Let’s start with the heart of the home – the kitchen. A typical kitchen remodel goes through a few stages: first, you’ve got the preliminary design phase, where we brainstorm ideas and figure out what you want. That usually takes around 5 weeks. Then comes the design development stage, where we get into the nitty-gritty details and finalize the plans – that’s about 4 weeks. After that, it’s time to roll up our sleeves and get to work on construction. Depending on what you’re doing, this phase can take anywhere from a few weeks to a couple of months.

Bathroom Remodels

Next up, let’s talk bathrooms. Like kitchens, bathroom remodels have a preliminary design phase (around 4 weeks) and a design development phase (another 4 weeks) before construction begins. Once we’ve nailed down the design, construction timelines can vary based on the scope of the project and other factors like material availability and any surprises we might encounter along the way.

Whole Home Renovation

Ready to give your entire home a facelift? A whole home renovation involves a bit more planning and coordination. The preliminary design phase for this type of project usually lasts around 6 weeks, followed by another 6 weeks for design development. Once the plans are locked in, construction can take several months, depending on the size of your home and the extent of the renovations.

Additions

Thinking about adding some extra space to your home? Adding an addition involves a similar process to remodeling, with a preliminary design phase (around 6 weeks) and a design development phase (another 6 weeks). If your addition requires engineering work, add an extra 2 weeks to the design phase. Construction timelines vary based on the size and complexity of the addition, but you can expect it to take several weeks to several months to complete.

Custom Home Build

Finally, if you’re starting from scratch with a custom home build, the process will take a bit longer. The preliminary design phase lasts around 6 weeks, followed by 8 weeks for design development (plus an extra 3 weeks if engineering is needed). Construction timelines for custom homes can span several months to over a year, depending on the size and complexity of the project.

Understanding the remodeling timelines in Corvallis for different types of renovations is essential for planning and managing your project effectively. Whether you’re sprucing up your kitchen, updating your bathroom, giving your whole home a makeover, adding an addition, or building a custom home, knowing what to expect in terms of timeframes can help you make informed decisions and keep your project on track. At Henderer Design + Build, we’re here to guide you through every step of the process and make sure your remodeling journey is as smooth and stress-free as possible. Reach out to us today to learn more about our services and how we can help bring your vision to life.

Share This Post

Download our Remodeling Cost Guide!

FREE COST GUIDE

For remodeling projects, additions, and
custom-built homes

Other articles you might like

You might enjoy seeing these projects...

Scroll to Top